10th and Flower street park

N Flower St & W 10th St
Groundbreaking date
2025
Construction period
February 2026 - Februrary 2027
Project description
The project features construction of a new 1.4-acre City park to provide the local community with access to open space, exercise, and recreation facilities. This park would be a walk-up, pedestrian park without a vehicle parking lot and would primarily serve the local neighborhood.
Grand opening
Spring/Summer 2026
Project components
- Basketball court
- Skate park
- Playground area with rubberized play surface
- Exercise area
- Canvas shade structures
- Turf play areas
- New site lighting
- Water wise landscaping with shade trees
- Automated irrigation system
- Site furnishings (including benches, bike racks, trash receptacles, drinking fountain and picnic tables, and a park monument sign)
Funding
- American Rescue Plan Act (ARPA)
- State of CA, Land & Water Conservation Fund Grant: $2.25m
- Acquisition & Development Funds – District II: $2.25m
- OCTA Measure M2 Tier 1 Env. Cleanup Program: $600,000
Project history
- Contract documents: 95% complete
- Bid advertisement: October 2025
- Bid opening: November 2025
- Construction contract award: December 2025
Help us name this park!
We are now seeking commmunity naming suggestions for this brand new park located on 10th and Flower Street. Submit your suggestion now and stay tuned to see if your name is a finalist. Sumbissions must meet specific criteria outline in the Santa Ana Municpal Code, view the list of guidelines required.