10th and Flower street park

Illustrative site plan of the proposed 10th & Flower Park in Santa Ana, showing a 1.4-acre layout with a playground and fitness areas with shade, basketball court, skate park, group gathering area, lawn, walkways, site furniture, lighting, and landscaping. Entries are on North Flower Street and 10th Street. An existing residential lot borders the northeast corner. North is oriented at the top.

N Flower St & W 10th St

Groundbreaking date

2025

Construction period

February 2026 - Februrary 2027

Project description

The project features construction of a new 1.4-acre City park to provide the local community with access to open space, exercise, and recreation facilities. This park would be a walk-up, pedestrian park without a vehicle parking lot and would primarily serve the local neighborhood.

Grand opening

Spring/Summer 2026

Project components

  • Basketball court
  • Skate park
  • Playground area with rubberized play surface
  • Exercise area
  • Canvas shade structures
  • Turf play areas
  • New site lighting
  • Water wise landscaping with shade trees
  • Automated irrigation system
  • Site furnishings (including benches, bike racks, trash receptacles, drinking fountain and picnic tables, and a park monument sign)

Funding

  • American Rescue Plan Act (ARPA)
  • State of CA, Land & Water Conservation Fund Grant: $2.25m
  • Acquisition & Development Funds – District II: $2.25m
  • OCTA Measure M2 Tier 1 Env. Cleanup Program: $600,000

Project history

  • Contract documents: 95% complete
  • Bid advertisement: October 2025
  • Bid opening: November 2025
  • Construction contract award: December 2025

 