City Hall Holiday Closure

Santa Ana City Hall is closed December 25, 2025, to January 2, 2026; there is no street sweeping December 25-26 and January 1. Go here to see all service impacts.  

What happens if the contractor changes or requires resubmittal of plans?

SolarAPP+ allows up to 3 revisions under the $35.00 fee.  They must resubmit the application to SolarAPP+ and once the resubmittal is approved, they will receive a modified permit number, for example:

    • Original SolarAPP+ ID: SA20230117-242-19-1234-A
    • First Approved Revision SolarAPP+ ID:SA20230117-242-19-1234-B
    • Second Approved Revision SolarAPP+ ID: SA20230117-242-19-C
    • Third and Last Approved Revision SolarAPP+ ID: SA20230117-242-19-1234-D

Once the contractor receives the new SolarAPP+ ID, a revision request is required through the City of Santa Ana PBx portal.  Click here to submit a request. All revision requests are processed within 72 business hours.